📄 Installation

Installation

Validate that the Softrim control cabinet is set up for the proper voltage of the plant being installed.

Step 1 - locate the vibratory conveyor in its final location.  Set the brakes on the two casters with brakes.

  

Step 2 - Attach vibratory conveyor controller and main control cabinet to the Deleafer frame.  These can be mounted on either the left or right side of the machine.  Install the yellow cable between the main control cabinet and the machine frame.


Step 3 - Orient the Deleafer assembly in front of the conveyor.  The oscillator motor on the rear door should be facing the conveyor.  Slide Deleafer assembly over the conveyor, until the white plastic "toes" on the conveyor caster frame align with the opening of the Deleafer frame.  Set the brakes on the Deleafer casters.


Step 4 - Verify alignment between Deleafer and Conveyor.  If the tray of the Conveyor touches the deleafer, it makes a very loud rattle.  It should look like the pictures below, from the rear of the assembly and looking up the conveyor, where gaps are the same on the left and right side.

 


Step 5 - Connect power cord on the conveyor caster frame to the cord on the conveyor controller.  Plug the conveyor controller into the bottom of the main control cabinet.  Finally, plug the main control cabinet into an outlet to power up the system.